EPSO
In connection with the reconstruction of the Shinuair substation and the Agarak substation to control the flow along the Agar 1 and Agar 2 lines, the organization of measurements at the Agarak substation to control the load of the 110 kV outgoing lines to the Shinuair substation and the generation of electricity at the Tatev HPP.